Proceedings
of the CSEWG & USNDP Meetings, BNL, November 4-7, 2008.
Edited by Pavel Obložinský, National Nuclear Data Center, BNL.
Summary Document (Minutes)
Presentations & Reports List of Participants & Photo
Agenda (CSEWG - green, USNDP - blue)
Nov 4, 2008, Tuesday, Berkner B
|
08:30 - 12:30 Berkner B
CSEWG Opening, Obložinský, 10'
Evaluation Committee (chair Chadwick), 3h
New format: We will focus, isotope by isotope, on updates for ENDF/B-VII.1 release, to occur in ~ 2010.
We will also discuss longer range updates planned for B/VII.2, especially for the major actinides.
- Overview comments and plans for VII.1, & ENDF/A, Chadwick, Herman, 15'
- Release files for ENDF/B-VII.0.fix1, Little, 15'
- B-VII.1 upgrade plans, All, 90'
- Update on IAEA standards group efforts, Carlson
- 6Li(n,t). Fix format error, Hale upgrade based on LANSCE data, issues related to changing standard: Hale/Chadwick, 1-2 slides
- 9Be. Insights from new RPI data, fix of VII.0 interpolation problem, future plans: Hale/Danon/Chadwick, 1-2 slides
- 16O. Comments on whether (n,a) should be changed and when? Note comments by Kolbe, PSI: Hale/Chadwick, 1 slide
- V. Anything new?
- 19F. Updates from ORNL and LLNL: Dunn/Leal/Firestone 1-2 slides
- 22Na. Resonance total width: who?
- Ti isotopes. B-VII.0 took Ti from JENDL3.3. New evaluations from LANL, testing in crits and pulsed spheres? ORNL 48Ti(n,g) - was this used? Note Danon exper. talk on total x/s at 0.5-20 MeV & need for res. energy shift: Kawano/Leal, 2 slides
- 55Mn. New ORNL evaluation, results, including comments on ZPR performance, BNL fast region, input from LLNL? Leal/McKnight/Pigni/Summers, 2 slides
- 35,37Cl. ORNL evaluation submitted Feb 07, has it been tested? Dunn/Leal, 1-2 slides
- 52,53Cr. ORNL measurements and plans to submit evaluation in FY09. Leal/Dunn, 1 slide
- Fe(n,a). Did B-VII.0 at higher energies use Haight (n,xa) data, if not - can we do this: Talou/Haight
- 58,60Ni. ORNL measurements and plans to submit evaluation in FY09: Leal/Dunn, 1 slide
- Gd. Note planned RPI capture expts this year; ORNL evaluation planned for 2010. Mosteller comments from reactor community experience.
- 90Zr. Should beta4 be released? Feedback from KAPL & Kozier, possible issues noted by Trkov. Note Danon exper. talk on nat-Zr total x/s at 0.5-20 MeV suggesting B/VI.8 was better: Pigni, 1-2 slides
- Cd. Adoption of BNL upgrade and positive results from data testing? Note Danon exper. talk on how RPI data support the change in the thermal region: Herman/Mughabghab/Mosteller, 1-2 slides
- 182,183,184,186W evaluations. ORNL resonance work, LLNL work, adoption of new IAEA evaluation? Herman/Leal/Firestone 1-2 slides
- Cu. LLNL evaluation. Testing against crits including Zeus? Summers, 1-2 slides. New Chinese evaluation: Chadwick
- Pu,U isotopes - fix fission spec above 10 MeV to have finer points: Chadwick, 1 slide
- 240Am new LLNL evaluation: Summers, 1 slide
- 241Am (n,g) upgrade - higher cross-section: Kawano, 1-2 slides
- MA. Possible adoption of certain Japanese minor actinide files, Kawano
- Possible modification to fission x.s. for 241Am, 237U,etc. based on LANL reaction rate crit assembly testing, and Japan FCA testing: Chadwick, 2 slides
- 237U from LLNL: Summers, 1-2 slides
- Possible Cum. FP yield upgrades of E&R for certain fission products: Chadwick, 1 slide
- 233U delayed neutron fix to B-VII.0 file: Little, 1 slide
- 237Np planned upgrade - (n,2n), chi? Anything else planned? Kawano/Chadwick, 1 slide
- Missing photon data erroneously not-carried-over from B-VI, and plans to include in B/VII.1: White, 1 slide
- S-alpha-beta in ENDF/B-VII.0 and in fix1. Comments, including observations from Physor08, Little, 1 slide
- B-VII.2 longer range plans, All, 45'
- 1H(n,p) scattering: Strakovsky, 10' + slide from Hale
- 2D. Any new data from Geel? Comments from Kozier, Hale
- 239Pu. Resonance region, including collaboration with JEFF: Leal, 1-2 slides
- 239Pu, 235,238U. Fission chi spectrum LANL/LLNL plans, 235U recent Geel exper, Shusaku Noda, 2 slides
- 239Pu,235,238U. 14 MeV inelastic scattering/preeq plans, Bethe sphere testing: Chadwick, 2 slides
- 235U.Capture update, WPEC subgroup: Kawano? 1 slide
- 238U.Capture & standard evaluation & Walner measurement: Chadwick comments
- 240Pu upgrade in fast region. Any testing results? Talou, 2-slides
- Actinide inelastic scattering in fast region, future theory and evaluation: Kawano, 1-2 slides
- Dy. ORNL measurements and plans to submit evaluation in FY11: Leal/Dunn, 1 slide
- The Temperature of Coherent Scattering Cross Sections, Lubitz, 15'
- Concluding discussion, 15'
12:30-14:00 Lunch break
CSEWG Executive Committee Working Lunch, 13:00-14:00, Berkner A
- Organizational matters
- Plans for ENDF/B-VII.1 release
- Next special issue of Nuclear Data Sheets
- WPEC matters
- Next meeting
14:00-17:30 Berkner B
Validation Committee (chair Kahler), 3h
- List of ENDF/B-VII.0 deficiencies, Herman, 15'
- LLNL validation, Descalle, 15'
- Benchmarking FENDL-2.1 with ENDF/B-VII.0 replacing VI.8, Sawan, 15�
- H-2 & UO2 Data Testing at AECL, Kozier, 15�
- Data Testing at ANL, McKnight , 15'
- ENDF/B-VII Nuclear Data Libraries in SCALE, Williams, 15�
- Data Testing at LANL, 50�
- Comments on ENDF/B-VII.0 deficiencies, Mosteller, 15�
- ICSBEP Benchmarks with Ti and V, Kahler, 10�
- Code Comparisons with Big-10, Kahler for MacFarlane, 10�
- Data Testing with the Official MCNP5 ENDF/B-VII Library, Kahler, 5�
- Physor2008 summary, Chadwick, 10'
- Comments on ENDF/B-VII.0 deficiences, Ignatyuk, 15'
- Other testing
|
Nov 5, 2008, Wednesday, Berkner B, Berkner C
| |
08:30- 12:30 Berkner B
Measurements Committee (chair Danon), 2.5h
- Nuclear data measurements at ANL, Kondev, 15'
- Status of cs standards measurements, Carlson, 15'
- Nuclear data experiments at LANSCE - Highlights 2008, Haight, 30'
- ORNL cross section measurement activities, Dunn, 15'
- LLNL experimental overview, Wu, 15
- Cross section measurements at Rensselaer, Danon 15'
- LBL thermal cs evaluations and measurements, Firestone, 15'
- EXFOR - compilation and issues, Hlavac, 10'
Formats & Processing Committee (chair Dunn), 1.5h
- Formats and related issues
- Processing Codes
- NJOY Status Report, Kahler, 15'
- AMPX Status Report, Wiarda and Dunn, 15'
- LLNL Status Report, McNabb, 15'
- ANL Status Report, McKnight, 15'
- Status report on PREPRO, TART and POINT, Cullen/Dunn, 5'
|
9:30-12:30 Berkner C
Informal round-table discussion (chair Tuli) 3h
- Guidance on use of new NDS band-drawing software, Geraedts
- Feedback on response to the new format
- Individual evaluators' questions regarding formats, procedures, data handling, etc.
|
12:30-14:00 Lunch break
13:30 Common Photo |
14:10-17:30 Berkner B
Formats & Processing Committee (chair Dunn), 0.5h
- BNL Activities Related to Formats and Processing
Covariance Committee (chair D. Smith), 2.5h
- CovCom website, D. Smith, 10'
- Covariance Workshop report, D. Smith, 15'
- BNL covariance effort, Obložinský, 15'
- Recent covariance evaluations at BNL, Pigni, 15'
- Recent covariance work at ORNL, Leal, 20'
- LLNL covariance overview, Vogt, 20'
- Recent covariance work at LANL, Talou, 30'
- Covariances of fission cross sections and nubars for actinides, Ignatyuk, 15'
|
14:00-17:30 Berkner C
USNDP Opening, Obložinský, 10'
14:10-17:30 Nuclear Structure WG (chair Baglin)
Status Reports:
- ENSDF & Nuclear Data Sheets, Tuli, 15'
- NSR, Bhattacharya, 15'
- Compilations: XUNDL & Atomic Masses, Singh, 15'
- NDS software: new band-drawings (1); proposed new Tables (2), Geraedts, 20'
- NuDat, Sonzogni, 15'
- ENSDF Analysis and Utility Codes, Baglin/Kibedi, 15'
Other Reports:
14:10-17:30 Berkner B
Nuclear Reaction WG (chair Kawano)
- Covariance evaluations, with CSEWG
|
Nov 6, 2008, Thursday, Berkner B, Berkner C
| |
08:30-12:30 Berkner B
Covariance Committee (chair D. Smith), 1.5h
- Covariances and neutron dosimetry: status and needs, Griffin, 20'
- Use of recent covariances in fast reactor studies, Aliberti, 20'
- Neutron spectrum covariances in uncertainty analyses, Yang, 20'
- Quality assurance of covariance files, Muir, 5'
- Partial contributions to total variance, Muir, 15'
- GNEP covariance library, Mattoon, 10'
- Sigma: covariance retrieval & visualization, Sonzogni, 10'
- Comedy of "Errors", D. Smith, 10'
Nuclear reaction modeling (chair Kawano), with USNDP
Concluding Session (chair Obložinský)
13:00 CSEWG adjourns
|
08:30-12:30 Berkner C
Nuclear Structure WG (chair Baglin)
Reports continued
Manpower
Outreach
- Outreach activities: FY08 achievements, FY09 plans, All, 15'
Other business/discussion?
End of Working Group Meeting
08:30-12:30 Berkner B
Nuclear Reaction WG (chair Kawano)
- Covariance evaluations, with CSEWG
- Nuclear reaction modeling, 1h
- State of EMPIRE, Herman, 15'
- New fission barrier calculation, Moller, 15'
- Reaction modeling at LANL, Kawano, 10'
- Fission spectrum modeling at LLNL, Vogt, 15'
- New version of SAMMY, Arbanas, 10'
|
12:30-14:00 Lunch break
USNDP Coordinating Committee Working Lunch, 13:00-14:00, Berkner A
- Organizational matters
- Situation in USNDP laboratories (all)
- Report FY08 & Workplan FY10
- Budget briefing FY11
- Next meeting
14:00-17:30 Berkner B
User Forum (chair Sonzogni)
|
Nov 7, 2008, Friday, Berkner B
| |
08:30-12:30 Berkner B
Reporting (chair Herman)
- USNDP web services, Pritychenko, 15'
- Task Force Reports (TF chairs, 15' each)
- Laboratory Reports (all, 10' each)
Concluding Session (chair Obložinský)
13:00 USNDP adjourns
|
|